Project: Waste Water Improvement Scheme
State: NSW
Services: Independent Estimating Services
Project Cost:AUD$170m
Date: 2006
The Project
The Coffs Harbour Sewerage Strategy was commissioned to improve and expand the sewerage system at a cost of approximately AUD$170m through to 2021. The project specification included a major upgrade of the Water Sewerage Treatment Plant from 42,000 equivalent persons (EP) to a 72,000 EP Water Reclamation Plant, to include both a capacity and a quality upgrade, the construction of a major pumping station at Sawtell and new sewer pipeline for the transfer of sewerage from Sawtell to the upgraded Coffs Harbour Water Reclamation Plant.
Our Involvement
We provided independent estimating services, and assisted with the risk management and analysis of costs for this project.
The Outcome
The project is still in progress.