Perth Airport Terminal Expansion Project

Built Environs is delivering the Perth Airport Terminal 1 Domestic Pier and International Departures Expansion project, the largest component of the airport’s $750 million redevelopment.

Our involvement

Aquenta Consulting was engaged to initially assist the Contract Administration Team set up processes to manage the extension of time provisions in the contract. We then managed this process within the strict contractual time frames. Aquenta have also been commissioned to provide measurement and estimating expertise on various trades including steelwork and civil works.

Services

Measurement and Estimating, Contract Administration, Contract Dispute Services.

The outcome

Testimony from the Project Commercial Manager, on Aquenta’s involvement:

“On behalf of the T1 Project team I would like to express my personal thanks to Andy for his dedication and hard work since he joined our team back in August last year. Andy joined the team at a time when our records and process needed improving and he went about his role with commitment and professionalism and without doubt his contribution over the period he has been here has helped us greatly to now be in a much more ordered and time compliant position.”

Aquenta continues to provide Contract Dispute Services to Built Environs relating to delay and disruption claims.